I have a flow where I am adding a row to an excel online (stored in sharepoint document library) file, using the 'Add a row into a table'.
Immediately after that action, I am copying the file to a different folder.
the problem is, the flow progresses past the action 'add a row into a table' before the file update is actually complete, so the copy of the file doesn't contain my most recent addition. If I look at the file I originally added the row to, the data is present there, which seems like an automatic indication that the copy file action started before the file update was complete.
Is there any way to work around this?
Hi @ dave-jorgensen,
Could you please share a screenshot of the configuration of your flow?
Please take a try to add a delay under the "Add a row into a table" action of Excel Online connector as screenshot below:
Please let me know if your issue could be solved.
Regards,
Alice Zhang
Hi Alice. No need for me to post a screen shot of flow - it looks exactly like yours.
I overcame the issues in the same way (adding a delay).
I guess I expected the 'adding a row to a table' to be a synchronous event, and that the flow would wait for that to actually complete before moving to the next action in the flow. Obviously that's not the case. Having to delay the flow artificially to overcome this works, but is pretty irritating and I'm sure causes lots of confusion / issues with users.
I understand that some actions, it's fine if they are asynchronous. Other times, users require an action to be synchronous, and certainly expect it to be so.
It would be ideal if actions had 2 things:
Really isn't a solution. The issue is, the flow doesn't wait for the action to complete.
putting in a delay is just recognizing that yes, the flow doens't wait for the action to complete, so we artificially wait. What if the 'behind the scenes' stuff in the action takes a long time, or server is slow, and now takes more than 1 minute? Then suddenly what you thought would work, doesn't. Extremely unreliable. That's why we need flow to actually wait for the action to complete
I'm having exactly the same problem. The question is i'm trying 5 sec delay, 20 sec delay, going to raise to 1 minute delay. But if the excel file has more lines than my test what delay time it will be the appropriate ?
Well i'm fighting with Flow to populate an excel file form a blank excel with a table inside and had lots of barriers.
Begining with the obligation to have a template in blank, beucase excel doesn't acepts dynamic data on the file location and now when i thougth, ok, lets arrange a workaround this happens.
Super frustrating.
Anybody ever come up with a better solution? As noted above, simply waiting doesn't guarantee that the updates actually occur. In the settings there is a an "Asynchronous Pattern" option, which I thought might change the behavior and force synchronous operation, but no such luck.
We've been aware of this and it continues to haunt us. If adding mutliple rows, we've had to add a delay between each row added so we don't innundate the server. Back searching for a setting to run the updates in synchronous mode, and have posted an idea on the FLOW Ideas site: https://powerusers.microsoft.com/t5/Flow-Ideas/Synchrous-Execution-IE-Excel-Add-Row-Sharepoint-Copy-.... Please vote it up.
In the mean time, we are just adding manual delays and crossing our fingers that they are long enough / we don't ever hit the server when it's too busy.
Hey @ryanperrymba
Have you found a solution for this? I have already voted up your idea. I've run into this problem multiple times now and it makes all my flow very unreliable!
Guess you could try:
The sad thing is, the connector can see the data as 'present' before it's actually written to the file. I have a Do-Until loop that uses the List Rows from a Table action to compare the number of rows to the expected value, and it's still missing a row in the final file. The row is present in the output of the last run of the Do-Until loop, but not in the spreadsheet file itself. Very frustrating! All I want to do is generate a spreadsheet and attach it to a list item...
They found a better solution for this synchronization problem, I had to create another flow that runs 5 minutes later, it is quite unreliable. ☹️
Just in case anyone was wondering, I tried using the Do Until to check to see when the file size has changed after I have inserted some rows in Excel and found this is not a reliable solution either. This is what I did after a series of "Add a row into a table":
Hoping someone comes up with something better
I thought about a solution, since I already know how many rows I need to have. Instead of adding a static delay, it's more reliable to add a wait until action and or do until control to wait for the count rows in the table. Ounce it hits the expected value then we get the content
Dear Community Members, We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd. During this period, members will not be able to Kudo, Comment, or Reply to any posts. On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities. What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!
We are excited to announce the Summer of Solutions Challenge! This challenge is kicking off on Monday, June 17th and will run for (4) weeks. The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities. Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”) - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024 Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods. You must enter into each weekly Entry Period separately. How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different. Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers. At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing. Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner. A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random. Individuals will be contacted before the announcement with the opportunity to claim or deny the prize. Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners. Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event. ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE** Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24 17 @Anil_g 7 @ManishSolanki 13 @eetuRobo 5 @David_MA 10 @VishnuReddy1997 5 @SpongYe 9JhonatanOB19932 (tie) @Nived_Nambiar 8 @maltie 2 (tie) @PA-Noob 2 (tie) @LukeMcG 2 (tie) @tgut03 2 (tie) Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate @Deenuji 12@ManishSolanki 19 @Anil_g 10 @NathanAlvares24 17 @VishnuReddy1997 6 @Expiscornovus 10 @Tjan 5 @Nived_Nambiar 10 @eetuRobo 3 @SudeepGhatakNZ 8 Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22 Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2 Anil_g2 SharonS2
On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners. The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights. Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.
We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for. We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer. Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together. Here's to new beginnings and endless possibilities! If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport. To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages