cancel
Showing results for 
Search instead for 
Did you mean: 
Reply
Anonymous
Not applicable

Have an Action Run in Parallel Without Duplicating The Action

Hi,

 

I have a flow that works in the following way:

 

  1. Scheduled Start Time
  2. Retrieve an excel file in SharePoint that contains a list of Parameters for use in next step (Customer Name, Email, etc)
  3. Apply to Each
    1. Take value from step 2
    2. Power BI Export Paginated Report to PDF for each row of the Parameters from step 2
    3. Send an Email, this takes the Email Address from the excel file and attaches the PDF of the paginated report

The workspace is going to be backed by an Embedded Capacity. Currently testing the cheapest node, A1.

 

I have test on A1 and A4, when I run the flow, the action of exporting the Paginated report to PDF takes 36 seconds in both cases. So they both take the same amount of time to run.

Looking at the CPU usage the stats are as follows:

 

A1 Node:

Peaked at 40% briefly

Average of 3.5% over the 70 Minutes it took to run

 

A4 Node:

Peaked at 7.4% briefly

Average of 0.6% over the 70 Minutes it took to run

 

So obviously, as embedded capacity is charged on a timely basis of the service being active, I would like to get the most out of the usage. And currently the usage is quite low on this task.

 

The result I would like is to have my step 3 run in parallel. I will keep my example simple and say I want to have two branches running at a time (In reality I would like as much as I can have running before it becomes an issue for performance)

 

I would like Branch 1 to run report numbers 1,3,5,7,9 etc.

And I want Branch 2 to run report numbers 2,4,6,8 etc.

So there is no duplication.

 

In my flow here, you can see the two branches but obviously setup this way, they are both running the same reports at the same time.

(Just as an FYI, The action to Export Paginated Report to PDF is only running a second slower for each report, so that is, each branch is producing a report every 37 seconds)

 

Can anyone point me in the right direction?

Do I need to somehow split the Excel file list first, or can I configure the flow at the Parallel stage rather?

 

ThanksCurrent PF Setup.png

 

 

1 ACCEPTED SOLUTION

Accepted Solutions
Anonymous
Not applicable

Unfortunately my lack of PA experience made me miss an obvious solution to this!

I did not have concurrency control enabled on my Apply to Each (degree of parallelism)
I enabled this and as expected, it ran multiple reports at once.

Run Reports in parallel 1.pngRun Reports in parallel 2.png

View solution in original post

4 REPLIES 4
Anonymous
Not applicable

I am considering adding in another column in the excel file that populates each row with an id number.

 

Call the Column something like "Branch Number"

Then get each Branch to filter on it's specific number to only run the rows associated with it.

 

But, if there is a better way to achieve this, please let me know.

Hi @Anonymous 

 

If you use length, you can get the number of rows in the value array returned by the excel action. Then you could div by 2 and create a range for both apply to each loops, range(0,div(length(value),2)) and range(add(1,div(length(value),2)).

 

Then call your objects in the apply to each as integer values, based on item() from the range. 

Hope that makes sense?

 

if not, I can try and mock up an example when I’m back home.

 

Please consider accepting my answer as a solution if it helps to solve your problem.

Cheers
Damien

Please take a look and subscribe to my YouTube Channel for more Power Platform ideas and concepts, or take a look at my website. Thanks

Anonymous
Not applicable

Hi DamoBird365,

 

Thank you for taking the time to respond, I really appreciate it.

 

Okay, I understand what you're doing with splitting the excel file. I just lose you slightly when it comes to the item()

If it's not too much trouble, I think a mock up would be very helpful.

 

Wrapping report SS1.png

 

I've added in the range, which then causes my Parameters, which are currently dynamic content of the required columns, to change and thus the flow fails -

 

Before the Range:

Wrapping report SS3.png

 

 

 

 

 

 

 

 

After the Range:

Wrapping report SS2.png

 

 

 

 

 

 

 

 

 

I'm not sure where to include the item() as when I do, it creates additional Apply to Each control, both to the "Export Paginated reports to PDF" and to the "Send an Email"

Anonymous
Not applicable

Unfortunately my lack of PA experience made me miss an obvious solution to this!

I did not have concurrency control enabled on my Apply to Each (degree of parallelism)
I enabled this and as expected, it ran multiple reports at once.

Run Reports in parallel 1.pngRun Reports in parallel 2.png

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!    This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24  17 @Anil_g  7 @ManishSolanki  13 @eetuRobo  5 @David_MA  10 @VishnuReddy1997  5 @SpongYe  9JhonatanOB19932 (tie) @Nived_Nambiar  8 @maltie  2 (tie)   @PA-Noob  2 (tie)   @LukeMcG  2 (tie)   @tgut03  2 (tie)       Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate  @Deenuji  12@ManishSolanki 19 @Anil_g  10 @NathanAlvares24  17 @VishnuReddy1997  6 @Expiscornovus  10 @Tjan  5 @Nived_Nambiar  10 @eetuRobo  3 @SudeepGhatakNZ 8     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22   Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2   Anil_g2   SharonS2  

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages