Power automate run on created or modified running multiple times

I have a power automate flow that runs when items are created or changed in a sharepoint document library. There is a trigger condition so it won't get stuck in a loop. This is an approval flow and there is about a minute lag time before the flow runs. If I make 2 changes within this time I end up with 2 approval flows running before the field from the trigger condition is updated to stop new flows from running. Is there a way ensure that it only runs once? 

1 ACCEPTED SOLUTION

Accepted Solutions

@wskinnermctc 

Remember that “When an Excel row is created, modified, or deleted workaround” template flow?

https://powerusers.microsoft.com/t5/Power-Automate-Cookbook/When-an-Excel-row-is-created-modified-or...

 

I think the 1st segment of the flow does just what is asked here. The flow includes a Delay as the 1st action which has the flow wait a set number of minutes, then it uses a Get file properties on the trigger file’s Id, then it has a condition check if the modified date from the updated pull is greater than the modified date of the initial trigger instance. If yes, then it uses the Terminate action to cancel the flow run as the next one is the most recent edit that should run with the rest of the flow.

Should work as intended here as long as you don’t mind a few minutes delay between the last edit & the rest of the flow / approval runs.

ExampleCancelRun.png

View solution in original post

4 REPLIES 4

Does this happen often? 

 

I don't have a solution, but it seems like it would be better to come up with a different process.

 

Like I'm thinking about people who set up flows that trigger on an email inbox when mail is received. It might take a few minutes for the flow to trigger after the email arrives. However, they need the flow to trigger immediately or it will be a problem with the overall process.

The only solution is to change the process of how they plan to do work. The plan should not require immediate email notice to function properly since that is not a capability they have.

 

You want this flow to trigger on some kind of specific file change using the broad trigger of whenever a file is changed. However, you're going to continue changing the file. You do have some kind of method for blocking future flows, but it doesn't happen fast enough. 

You are limited by the speed of when a flow can trigger. That is not going to change.

 

The process you want to implement needs to change due to system limitations.

 

Like instead of using the active file to trigger the flow, could you use like a drop folder or something that uses a second copy file? So maybe when you drop a file in the folder it triggers an approval flow. Either the flow runs off that document or whatever. Or you could maybe hyperlink the approval back to the active document? 

 

I really don't know how to change it, but I think a change to the process would be better.

Bc I can't think of a way to prevent Action2 from happening when it is conditional on a result from Action1; when Action1 has not even been initiated.

 

Who knows, maybe some power automate wizard will come step on me with some fancy tricks and solution.

@wskinnermctc 

Remember that “When an Excel row is created, modified, or deleted workaround” template flow?

https://powerusers.microsoft.com/t5/Power-Automate-Cookbook/When-an-Excel-row-is-created-modified-or...

 

I think the 1st segment of the flow does just what is asked here. The flow includes a Delay as the 1st action which has the flow wait a set number of minutes, then it uses a Get file properties on the trigger file’s Id, then it has a condition check if the modified date from the updated pull is greater than the modified date of the initial trigger instance. If yes, then it uses the Terminate action to cancel the flow run as the next one is the most recent edit that should run with the rest of the flow.

Should work as intended here as long as you don’t mind a few minutes delay between the last edit & the rest of the flow / approval runs.

ExampleCancelRun.png

See! @iwannabfishn told you some wizard would come along lol! It's like I manifested him!

 

@takolota I really did think up this same solution about delays, and started typing about it, but I stopped. I was thinking that it was possible for the second flow to get through.

But I didn't consider modified datetime, I was thinking to recheck whatever that condition that is stopping the trigger. Like I thought some property "InProcess" or something was getting populated by the first flow to be the trigger condition for anything behind. I didn't trust it getting populated in time.

 

(Also I don't know why I envisioned all of this was dealing with a MS Word document approval. Type of file was never mentioned.)

 

That's why you're the wizard! I'll go back to answering questions about datetime format where I belong 🙃

@wskinnermctc 

 

I mean I started a few years ago by writing some hack-ish expressions to try capitalizing the 1st letter of names & ensuring lowercase on all other letters before I watched a lot more Jon Levesque, Reza Dorrani, & Paul Murana videos and developed more of my own templates for practice.

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!    This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24  17 @Anil_g  7 @ManishSolanki  13 @eetuRobo  5 @David_MA  10 @VishnuReddy1997  5 @SpongYe  9JhonatanOB19932 (tie) @Nived_Nambiar  8 @maltie  2 (tie)   @PA-Noob  2 (tie)   @LukeMcG  2 (tie)   @tgut03  2 (tie)       Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate  @Deenuji  12@ManishSolanki 19 @Anil_g  10 @NathanAlvares24  17 @VishnuReddy1997  6 @Expiscornovus  10 @Tjan  5 @Nived_Nambiar  10 @eetuRobo  3 @SudeepGhatakNZ 8     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22   Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2   Anil_g2   SharonS2  

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (1,787)