cancel
Showing results for 
Search instead for 
Did you mean: 
Reply

Reminder Emails While Status = In Progress

SharePoint list where Status column = In Progress or Complete. 

 

If Status = In Progress, and 7 days has passed, I want an email reminder to trigger, otherwise if Status = Complete, no email. 

 

I created a column titled "7" that calculates the +7 days date. 

 

I'm using an Automated flow When New Item Added "Do Until" status = Complete, but it's only firing when the item is first entered.  It's not running daily. 

 

Using utcNow('MM/dd/yyyy') to compare to the "7" date.  MM/dd/yyyy is how the date columns are displayed. 

 

What am I missing (see image)?

 

2020-10-28_8-59-45.jpg

 

 

 

 

 

 

 

1 ACCEPTED SOLUTION

Accepted Solutions

@tom_riha 

 

Got it working. THANK YOU, THANK YOU, THANK YOU. I cannot express how much this has been a journey, and you’ve been my flow Sherpa! 


I am recapping your help here so it's condensed for solution. 

 

  1. Do not use a calculated column.  Plain date column only. 

  2. Create a Scheduled flow to run daily. 

  3. Add "Get Items" and select Site Address and List Name.

  4. In the Filter Query section, manually type:  Status eq 'In progress' and Today eq then use the expression builder to add:  addDays(utcNow(),-7,'MM/dd/yyyy')  (where In Progress and Today are your column titles)

  5. After it has inserted the expression, manually type single quotes around the pink box:

scnative_0-1604353676996.png

 

6. Add an Apply to Each step after the above. *Select an output from previous steps will be dynamic Value.

value.jpg

7. Add Send an Email and enter dynamic details.  

 

8. Click Save.

 

Here's how it looks completed:

 

whole.jpg

View solution in original post

18 REPLIES 18
tom_riha
Most Valuable Professional
Most Valuable Professional

I think for reminders it’s better to create a ‘Scheduled’ flow that will run once a day, filter all relevant items and send notifications. A flow with the following structure:

  • Scheduled trigger, run daily
  • Get items, with filter query: 7 eq ‘utcNow...’ and status eq ‘In progress’
  • Apply to each
    • Send an email


[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

Thanks.  @tom_riha I looked up data on "apply to each" but am unsure what is wrong, as the flow failed. 

 

Is it supposed to add 2 of the "apply to each" actions?  Or did I fat-finger it?

 

I'm confused on which value I am applying to each and why?

 

 

flow.jpg

tom_riha
Most Valuable Professional
Most Valuable Professional

One 'Apply to each' action should be enough, the one called 'Apply to each 2' in your flow. By default 'Apply to each' action needs an array as input, which is the 'value' dynamic content coming out of the 'Get items'.

I guess the 2nd Apply to each (called 'Apply to each') with 'Status' as an input is failing since 'Status' is not an array.

In general, when building Power Automate flows the flow will add the 'Apply to each' actions by itself when needed. You need to add it manually only if you're using your own array variables.



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

Me again @tom_riha.  🙄

 

Flow failed:  The expression "  Status eq 'In Progress' and 7 eq ‘utcNow('MM/dd/yyyy')’  " is not valid. 

I've read that when reporting utcNow the month should be capitalized MM- does it matter?
Could the error be because the 7 date column is calculated?

 

tom_riha
Most Valuable Professional
Most Valuable Professional

That's a good point, it'll not work with calculated column. Calculated columns are not supported in the Filter Query, if you need to do some calculation you must do it directly in the Filter Query and use the original date column. So instead of just utcNow(...), you need to extend it by addDays() expression to do the calculation (the code below will remove 7 days from today's date).

addDays(utcNow(),-7,'MM/dd/yyyy')

image.png

Month should be capital M, lower-case m are minutes.



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

Hi @tom_riha

 

Okay so get this.  During one of my tests a few minutes ago that failed on input, it showed the OLD list name.  Hasn't since.  I think this is why it's failing.  I was asked to change the list name couple days ago.  I've had issues with Power Automate and Power Apps not updating accordingly when column name changes.  They retain the old names and I have to rebuild stuff to compensate.  Anyway, I didn't copy it when I saw it, thought I could reproduce, but it's hasn't. 

 

What is your recommendation?  It's really tiring to get these "well, that's just how it is!" errors.  Apps seem shoddy, at best.  

 

Thanks!

tom_riha
Most Valuable Professional
Most Valuable Professional

I think renaming lists and columns shouldn't be a problem in Power Automate, it doesn't use display names of lists and columns, it's using GUID for lists and internal names for columns. These are fixed for the whole existence time of the list/column. The only way to change them would be to delete and create new list/column.

I can't talk for Power Apps though, I don't like them very much as they're very 'shoddy' as you say and I totally agree. 



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

Agreed.  I'm still getting this error, though. 

 

The expression "Status eq 'In progress' and 7 eq 11/06/2020" is not valid. Creating query failed.

 

Where the date is calculated in the Filter Query

addDays(utcNow(),7,'MM/dd/yyyy')
 
(changed to +7 due to requirements)

@tom_riha 

 

What could be causing this?  flowwoes.jpg

@tom_riha 

 

Could it be because it says there's no dynamic content, thus no way for me to add the column Status that way.  I manually typed it in.  

flowwoes2.jpg

tom_riha
Most Valuable Professional
Most Valuable Professional

Is ‘7’ still calculated column or you changed it to date only column?

The Status column is a choice column? In the query filter you don’t need dynamic content, you have to type in everything by yourself and the Status part seems fine to me. 
Maybe you could try to run only the Status filter, then only the date filter, and you’ll see which one fails. 



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

@tom_riha  Hi again. 

 

I wasn't aware calculated column needed to be changed to date only if the formula is ODATA. 

 

How do I extract the date as a date, versus the calculated?   I've been looking up tuts on it, but cannot figure it out and need to get this out the door as soon as possible. 

tom_riha
Most Valuable Professional
Most Valuable Professional

The calculated column must be based on some date where you add the 7 days. Use the same date column you use in the calculated field in the filter.

E.g. let's call it AssignedDate, then currently your calculated column 'seven' will be something like  'seven' =[AssignedDate]+7. Then you're trying to use the following formula in the filter: 'seven' == [today], which won't work (due to the calculated column). You need to do the calculation on the other side of the formula: AssignedDate == [today]-7, that means AssignedDate == addDays(utcNow(),-7,'MM/dd/yyyy').  <= that's an expression.

The right side of the formula in the filter must be always a basic SP column, all operations must be done on the left side.



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

@tom_riha 

 

I REALLY appreciate your patience with me on this. 

 

So I'm an idiot, as is evident... 😂  I see your point now.  

 

I have an Input Date (not calculated) column.  So, applying the calc in ODATA on *that* column is what I need to be working on. 

 

I tried:  

 

Status eq 'In progress' Input Date eq addDays(utcNow(),-7,'MM/dd/yyyy' and it failed. 

 

I tried putting single quotes around the addDays... and it failed, too.  

 

 

tom_riha
Most Valuable Professional
Most Valuable Professional

Almost there. 🙂

1. you're missing 'and' between the formulas

2. you must use internal name of the 'Input Date' column (check column settings, it's at the end of the URL after 'Field=')

3. I'm not sure if the addDays(... was entered as an expression, but it must be an expression

It should look in a similar way as in the message 6, including all apostrophes.



[ If I have answered your question, please Accept the post as a solution. ]
[ If you like my response, please give it a Thumbs Up. ]

[ I also blog about Power Automate solutions even for non-IT people. ]

 

@tom_riha 

 

I added single quotes around the UTC expression and the flows are succeeding!!!!!  

 

THANK YOU, THANK YOU, THANK YOU!!!!!  

 

I will post a recap shortly to keep all correct data in one post.  If you could copy/paste what I post as a reply to this, then you'll get credit for the knowledge and I'll mark as solution. 

 

 

@tom_riha 

 

Got it working. THANK YOU, THANK YOU, THANK YOU. I cannot express how much this has been a journey, and you’ve been my flow Sherpa! 


I am recapping your help here so it's condensed for solution. 

 

  1. Do not use a calculated column.  Plain date column only. 

  2. Create a Scheduled flow to run daily. 

  3. Add "Get Items" and select Site Address and List Name.

  4. In the Filter Query section, manually type:  Status eq 'In progress' and Today eq then use the expression builder to add:  addDays(utcNow(),-7,'MM/dd/yyyy')  (where In Progress and Today are your column titles)

  5. After it has inserted the expression, manually type single quotes around the pink box:

scnative_0-1604353676996.png

 

6. Add an Apply to Each step after the above. *Select an output from previous steps will be dynamic Value.

value.jpg

7. Add Send an Email and enter dynamic details.  

 

8. Click Save.

 

Here's how it looks completed:

 

whole.jpg

Hi all,

 

I am new to Power Automate and would like to explore it because it is interesting. 

 

My case is, I want to send an email notification to admins that will occur every 10:00 in the morning everyday, if there are 'In-progress' items that are unassigned to them.

Just want to ask what is the issue on my first flow. I'm having an error.

davidkarn_0-1626423557149.png

 

Any help or advice is well appreciated. Thank you

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!    This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24  17 @Anil_g  7 @ManishSolanki  13 @eetuRobo  5 @David_MA  10 @VishnuReddy1997  5 @SpongYe  9JhonatanOB19932 (tie) @Nived_Nambiar  8 @maltie  2 (tie)   @PA-Noob  2 (tie)   @LukeMcG  2 (tie)   @tgut03  2 (tie)       Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate  @Deenuji  12@ManishSolanki 19 @Anil_g  10 @NathanAlvares24  17 @VishnuReddy1997  6 @Expiscornovus  10 @Tjan  5 @Nived_Nambiar  10 @eetuRobo  3 @SudeepGhatakNZ 8     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22   Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2   Anil_g2   SharonS2  

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (1,255)