How to add an entity to the available activity types in a timeline control?

I realize I posted this in the wrong forum, so I've made the topic over here.

 

In case there's a better way than I'm attempting below; my end goal is that I can select a building entity record, and then add multiple records of another entity to it in quick succession. Similar to how you can add multiple notes to a record using the timeline control. If there's another way to do this, I would be fine trying it out.

 

I feel like this is probably very easy to do but I must be missing something. I've got two custom entities. One is for each of our buildings. Another is going to be for capturing information when we visit that building in person. 

 

On the record for the building, I would like the timeline control, without the notes, but instead have our custom entity for visits. Can someone tell me how to do that? 

 

I  tried making an activity entity but I couldn't figure out how to add it as an option to the timeline. I also do not know how to take the Notes activity off of the timeline.

 

I've tried editing the Timeline control on my "Building" custom entity in the classic view, but I can neither remove the Notes nor add other activity entities.

 

2020-01-21 07_49_58-Form_ SiteVisitDetails.png

1 ACCEPTED SOLUTION

Accepted Solutions
HSheild
Most Valuable Professional
Most Valuable Professional

Hi @notj 

 

I will touch on 2 different approaches

 

Activities in the timeline

  • To get the custom activity to appear in the Timeline have you followed all of the steps here?  There are a number of things you need to do like add to your model-driven app and enable Display in Activity Menu
  • I don't think you are able to remove the Notes from the Timeline for a Model-driven app.  The Dynamics 365 model-driven apps have an extra entity which shows in the Timeline called Posts which normal Model-Driven apps don't.  In Dynamics 365 you can toggle the Default Module for Create Experience to either Notes or Posts.

Alternative approach

  • Build your Building Visit entity as a normal entity (not activity)
  • Enable your Building Visit entity for Quick Create and create a Quick Create form for it
  • Also create a Card form for your Building Visit entity https://docs.microsoft.com/en-us/powerapps/maker/model-driven-apps/create-card-forms
  • Create a 1:N relationship between the Building entity and the Building Visit entity
  • Make the Building field on the Building Visit entity Business Required
  • On your Building form place a subgrid which points to Building Visits
  • You can then experiment with the Controls property on the subgrid to display it in different formats
  • Subgrid control.png

A  lot of steps but it is quite straight forward once you get the hang of it.  I ended up getting carried away and building an example - it's very quick. You will then end up with something like the screenshots below without the complicated Timeline control.  You can quickly add new Visit records from a subgrid on the Building form and then display in a timeline type view using Card forms and the Read-Only Grid Control in the subgrid.

Let me know if you need any further help.

 

Annotation 2020-01-23 204425.png

 

Subgrid control 2.png

 

Annotation 2020-01-23 204359.png

 

View solution in original post

3 REPLIES 3
Anonymous
Not applicable

Have you enabled the activities for the building entity? Check the properties of the entity. 

 

After the activities are enabled you should be able to filter only activities to be displayed on the timeline control on the building form.

HSheild
Most Valuable Professional
Most Valuable Professional

Hi @notj 

 

I will touch on 2 different approaches

 

Activities in the timeline

  • To get the custom activity to appear in the Timeline have you followed all of the steps here?  There are a number of things you need to do like add to your model-driven app and enable Display in Activity Menu
  • I don't think you are able to remove the Notes from the Timeline for a Model-driven app.  The Dynamics 365 model-driven apps have an extra entity which shows in the Timeline called Posts which normal Model-Driven apps don't.  In Dynamics 365 you can toggle the Default Module for Create Experience to either Notes or Posts.

Alternative approach

  • Build your Building Visit entity as a normal entity (not activity)
  • Enable your Building Visit entity for Quick Create and create a Quick Create form for it
  • Also create a Card form for your Building Visit entity https://docs.microsoft.com/en-us/powerapps/maker/model-driven-apps/create-card-forms
  • Create a 1:N relationship between the Building entity and the Building Visit entity
  • Make the Building field on the Building Visit entity Business Required
  • On your Building form place a subgrid which points to Building Visits
  • You can then experiment with the Controls property on the subgrid to display it in different formats
  • Subgrid control.png

A  lot of steps but it is quite straight forward once you get the hang of it.  I ended up getting carried away and building an example - it's very quick. You will then end up with something like the screenshots below without the complicated Timeline control.  You can quickly add new Visit records from a subgrid on the Building form and then display in a timeline type view using Card forms and the Read-Only Grid Control in the subgrid.

Let me know if you need any further help.

 

Annotation 2020-01-23 204425.png

 

Subgrid control 2.png

 

Annotation 2020-01-23 204359.png

 

The alternative approach you documented works perfectly. Thanks so much @HSheild !

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!   This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions in the Forums to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber of SolutionsSuper UsersNumber of Solutions @anandm08  23 @WarrenBelz  31 @DBO_DV  10 @Amik  19 AmínAA 6 @mmbr1606  12 @rzuber  4 @happyume  7 @Giraldoj  3@ANB 6 (tie)   @SpongYe  6 (tie)     Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersSolutionsSuper UsersSolutions @anandm08  10@WarrenBelz 25 @DBO_DV  6@mmbr1606 14 @AmínAA 4 @Amik  12 @royg  3 @ANB  10 @AllanDeCastro  2 @SunilPashikanti  5 @Michaelfp  2 @FLMike  5 @eduardo_izzo  2   Meekou 2   @rzuber  2   @Velegandla  2     @PowerPlatform-P  2   @Micaiah  2     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 3:Community MembersSolutionsSuper UsersSolutionsPower Apps anandm0861WarrenBelz86DBO_DV25Amik66Michaelfp13mmbr160647Giraldoj13FLMike31AmínAA13SpongYe27     Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 4:Community MembersSolutionsSuper UsersSolutionsPower Apps DBO-DV21WarranBelz26Giraldoj7mmbr160618Muzammmil_0695067Amik14samfawzi_acml6FLMike12tzuber6ANB8   SunilPashikanti8

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (1,717)