Hello!
Having trouble wrapping my head around what I need to do.
I have an approval process that has several levels of sequential approver groups. For example:
User uploads a document to a SharePoint library
Approval process begins with Project Managers. When they approve, the Supply Chain folks need to approve, when they approve, the Deployment folks will need to approve and so on for about 11 levels.
These approvals for the most part will wrap up within the 30 day time limit but there are many instances where the approval could be sitting with an approver group for 2-4 months.
Now I saw where we can use the Start and Approval and then use the CDS to wait for an action to happen. I read the article where it shows you would use 2 power automates to use this (Build long-running Approval Flows - Power Platform Community (microsoft.com)). But it only shows for a single level of approvals.....
So my issue is, how would this work with multiple levels of approval that need to happen in a specific sequence? Will I need to create 22 workflows? And even then how would I make sure they execute in the proper order?
Is there some other way perhaps to get this to work? Just looking for suggestions on how to proceed as I can't seem to figure out what I need to do.
As always thanks!
Solved! Go to Solution.
Not quite. Flow A would create the first approval in the series and record the overall status somewhere, lets call it stage 1. Flow B would wait for the Approval object in CDS to change. When it changes it would check the response and the overall status (which is now stage 1) and either create a new Approval and set status to Stage 2 or Stop the approval because it was rejected. Flow B would then wait for the Approval object in CDS to change. Repeat until all stages are complete.
Flow B will fire whenever any Approval record changes. That's why I would suggest a separate entity that tracks the current stage of the process. The Approval ID can be looked up in that when Flow B triggers.
The process is essentially the same. And you'll still really only need two flows. But you'll need to add some logic to the second flow that determines who responded to the approval and who is next in line or whether you are done. you'll also need to create an entity that can keep track of the progress so you can determine where you are and who is next. But the key is to separate the creation of the approval from the processing of the response. Having multiple levels increases the complexity a bit, but it can still be done with two flows.
Ok so I would make 1 flow that would create all of the approvals I need....and the 2nd flow would need to do all the rest of the work...
So Flow A - 11 Start Approvals
Flow B - I would need to work out sending the email notice to each approving group in the right order, wait on their response and then move to the next set of approvers? But how do I determine that?
The article shows using the When a Record is Updated - but I see no way to specify which approval record I'm looking for...there was no ID or anything. I must be missing something somewhere lol
Thanks!
Not quite. Flow A would create the first approval in the series and record the overall status somewhere, lets call it stage 1. Flow B would wait for the Approval object in CDS to change. When it changes it would check the response and the overall status (which is now stage 1) and either create a new Approval and set status to Stage 2 or Stop the approval because it was rejected. Flow B would then wait for the Approval object in CDS to change. Repeat until all stages are complete.
Flow B will fire whenever any Approval record changes. That's why I would suggest a separate entity that tracks the current stage of the process. The Approval ID can be looked up in that when Flow B triggers.
Ah ok i think i understand better now - will give it a go!
Thanks!! 🙂
Currently, I'm working on a PowerAutomate sequential approval flow.
Problem statement:-
There are totally 5 levels of approval, the recipient of the approvals are dynamically set in Flow.
Now the level the approval needs to go depends on two variable in the SharePoint list. One is the deal status and the other is by project cost. I have the matrix build in another SharePoint list if this helps. looking for guide as my flows are showing infinite loop error as currently written.
If any recipient denies the project the project must show rejected with comments on rejection. Only once approved by all can the project show approved. Is there any way that this particular thing can be achieved?
Thanks,
Please post this as a new question. You'll get more responses and others will be able to find the answer more easily later.
Dear Community Members, We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd. During this period, members will not be able to Kudo, Comment, or Reply to any posts. On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities. What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!
We are excited to announce the Summer of Solutions Challenge! This challenge is kicking off on Monday, June 17th and will run for (4) weeks. The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities. Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”) - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024 Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods. You must enter into each weekly Entry Period separately. How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different. Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers. At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing. Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner. A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random. Individuals will be contacted before the announcement with the opportunity to claim or deny the prize. Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners. Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event. ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE** Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24 17 @Anil_g 7 @ManishSolanki 13 @eetuRobo 5 @David_MA 10 @VishnuReddy1997 5 @SpongYe 9JhonatanOB19932 (tie) @Nived_Nambiar 8 @maltie 2 (tie) @PA-Noob 2 (tie) @LukeMcG 2 (tie) @tgut03 2 (tie) Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate @Deenuji 12@ManishSolanki 19 @Anil_g 10 @NathanAlvares24 17 @VishnuReddy1997 6 @Expiscornovus 10 @Tjan 5 @Nived_Nambiar 10 @eetuRobo 3 @SudeepGhatakNZ 8 Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22 Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2 Anil_g2 SharonS2
On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners. The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights. Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.
We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for. We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer. Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together. Here's to new beginnings and endless possibilities! If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport. To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages