Hi all,
Is it possible to set the 'Delay' function to working days (mon-fri) only? I can see the option for days, but there's also a custom field, so hoping there might be something i can add here to set the days function to work days only.
Any help will be appreciated!
Thanks
Sophie
Hi there - So, the "Enter Custom Value" is kind of standard on most dropdowns. I don't think there is an option for weekdays only...BUT, that doesn't mean you can't do it. What you may want to consider is to have a "Compose" step before that calculates out the delayed date, and then using the "Delay Until" action to reference that calculated date.
You can absolutely combine those steps, but I just thought that might be easier.
How long of a delay did you want?
-Ed
Thanks @edgonzales
I'm looking to have a 4 day delay. I want to give a particular team 4 days to action something, but exclude Saturday and Sunday from the calculation.
Does the 'Delay until' have to run on a specific date or does that allow a certain number of days?
Thanks
Sophie
Do you want the following if the current day is:
If so, you can do this by:
Your flow will look like this:
Thanks @David_MA
This definitely looks like it'll work exactly how i need it too. I haven't started building the flow yet, i just needed to know it was possible before i made a start on it, so this has really helped!
In the condition, does the 0 and the 1 represent Sunday and Monday then? I've not used numbers to represent the days of the week in a flow before.
Thanks
Yes, when you use the dayOfWeek expression it returns a number with 0 being Sunday, 1 being Monday, etc.
If you want to simplify this, you could just use the following expression in your delay action:
if(greater(1,dayOfWeek(triggerBody()['date'])),'4','6')
You would replace (triggerBody()['date']) with your date field.
I think you are asking what the expressions would be, correct? If not, I show the flow in my original response below. If you are asking for the expressions, you can greatly simplify things by just putting this expression in your delay action:
if(greater(1,dayOfWeek(triggerBody()['date'])),'4','6')
You would replace triggerBody()['date'] with the date field used to determine the delay from.
I showed the long way at first as that is a better way of learning how to use Power Automate and build flows so you learn some of the concepts. It also better illustrates the logic.
hi @David_MA
You helped with this a while back and i'm finally at this stage of the flow and need a little more support if that's ok?
I've tried to replicate the flow in your image above but i'm getting the error 'string must match ISO 8601 format'
Could you tell me how you've set up the expressions/formulas (not sure of correct terminology!) in the sections i've circled in your image below please?
The data i have coming in from excel is in the format '15/03/2023 15:56:16' as an example
Many thanks,
Sophie
You need to format the data from your Excel string of '15/03/2023 15:56:16' to return the day of the week; is that correct? ISO dates need be in the format of yyyy-MM-dd so you will need to manipulate the Excel data to the correct date format. This should not be too hard by using a couple of expressions.
The first expression will take your Excel string and extract just the date portion and split it by the slash. That formula would be (note, replace triggerBody()['text'] with the dynamic data from Excel):
split(slice(triggerBody()['text'],0,10),'/')
The second expression will then take the output, format it as an ISO date and return the day of the week (note: the above expression is in a Compose action that is named Compose_Get_Date_Components. If you name your compose actions something different, you will need to adjust the expression accordingly):
dayOfWeek(concat(outputs('Compose_Get_Date_Components')[2],'-',outputs('Compose_Get_Date_Components')[1],'-',outputs('Compose_Get_Date_Components')[0]))
This is the flow I used to illustrate the above:
Which returns:
Dear Community Members, We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd. During this period, members will not be able to Kudo, Comment, or Reply to any posts. On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities. What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!
We are excited to announce the Summer of Solutions Challenge! This challenge is kicking off on Monday, June 17th and will run for (4) weeks. The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities. Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”) - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024 Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods. You must enter into each weekly Entry Period separately. How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different. Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers. At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing. Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner. A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random. Individuals will be contacted before the announcement with the opportunity to claim or deny the prize. Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners. Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event. ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE** Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24 17 @Anil_g 7 @ManishSolanki 13 @eetuRobo 5 @David_MA 10 @VishnuReddy1997 5 @SpongYe 9JhonatanOB19932 (tie) @Nived_Nambiar 8 @maltie 2 (tie) @PA-Noob 2 (tie) @LukeMcG 2 (tie) @tgut03 2 (tie) Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate @Deenuji 12@ManishSolanki 19 @Anil_g 10 @NathanAlvares24 17 @VishnuReddy1997 6 @Expiscornovus 10 @Tjan 5 @Nived_Nambiar 10 @eetuRobo 3 @SudeepGhatakNZ 8 Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22 Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2 Anil_g2 SharonS2
On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners. The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights. Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.
We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for. We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer. Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together. Here's to new beginnings and endless possibilities! If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport. To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages