cancel
Showing results for 
Search instead for 
Did you mean: 
Reply

Set a date and exclude weekends and vacation days

Hello,

 

I have an application which aims to set a task end date.

To define this date I must enter the number of days and then exclude weekends and holidays which are registered in a sharepoint list.

 

I have set up two calculation formulas but it does not work I would like your help.

 

Formula 1 :

the first datapicker is the departure date and the second is the calculated date 

date 2.jpg

 

Spoiler
With({startDate:DatePicker_1.SelectedDate;daysToAdd:Value(TextBox_75.Text)};
DateAdd(startDate;daysToAdd)+RoundDown(daysToAdd/5;0)*2+
Switch(Weekday(startDate;StartOfWeek.Monday);5;
If(Mod(daysToAdd;5)>0;2;0);4;
If(Mod(daysToAdd;5)>1;2;0);3;
If(Mod(daysToAdd;5)>2;2;0);2;
If(Mod(daysToAdd;5)>3;2;0);1;
If(Mod(daysToAdd;5)>4;2;0))
+
CountIf(Holiday;HolidayDate>=startDate;HolidayDate<=startDate))

Formula 2 :

the first datapicker is the departure date and the second is the calculated date 

date1.jpg

Spoiler

DateAdd(DatePicker_1.SelectedDate;
Value(TextBox_66.Text) +
RoundDown(Value(TextBox_66.Text) / 5; 0)*2+
Switch(Weekday(DatePicker_1SelectedDate);5;If(Mod( Value(TextBox_66.Text) ; 5)>0;2;0);
4;If(Mod( Value(TextBox_66.Text) ; 5)>1;2;0);
3;If(Mod( Value(TextBox_66.Text) ; 5)>2;2;0);
2;If(Mod( Value(TextBox_66.Text) ; 5)>3;2;0);
1;If(Mod( Value(TextBox_66.Text) ; 5)>4;2;0))
)+


CountIf(
Holiday;
HolidayDate >= DateAdd(DatePicker_1.SelectedDate;
Value(TextBox_66.Text) +
RoundDown(Value(TextBox_66.Text) / 5; 0)*2+
Switch(Weekday(DatePicker_1.SelectedDate);5;If(Mod( Value(TextBox_66.Text) ; 5)>0;2;0);
4;If(Mod( Value(TextBox_66.Text) ; 5)>1;2;0);
3;If(Mod( Value(TextBox_66.Text) ; 5)>2;2;0);
2;If(Mod( Value(TextBox_66.Text) ; 5)>3;2;0);
1;If(Mod( Value(TextBox_66.Text) ; 5)>4;2;0))
);
HolidayDate <= DateAdd(DatePicker_1.SelectedDate;
Value(TextBox_66.Text) +
RoundDown(Value(TextBox_66.Text) / 5; 0)*2+
Switch(Weekday(DatePicker_1.SelectedDate);5;If(Mod( Value(TextBox_66.Text) ; 5)>0;2;0);
4;If(Mod( Value(TextBox_66.Text) ; 5)>1;2;0);
3;If(Mod( Value(TextBox_66.Text) ; 5)>2;2;0);
2;If(Mod( Value(TextBox_66.Text) ; 5)>3;2;0);
1;If(Mod( Value(TextBox_66.Text) ; 5)>4;2;0))
)
)

The week starts on a Monday and the sharepoint list which includes vacation days is HolidayDate

1 ACCEPTED SOLUTION

Accepted Solutions
timl
Super User
Super User

@EdouardVH 

In terms of accounting for public holidays, adding the holiday days to weekDaysToAddAbs will be what you need.

 

That is because if you're subtracting days, you don't want to add the holiday days to the final end result because you'll end up adjusting the result in the wrong direction (ie, you want to subtract the holiday days).

 

===

With({weekDaysToAdd: -18},
With(
{ weekDaysToAddAbs: Abs(weekDaysToAdd) + CountIf(Holiday;HolidayDate>=startDate;HolidayDate<=startDate) ,
startDate:Date(2021,11,30) },
With(
{
fullWeeks: RoundDown(weekDaysToAddAbs / 5, 0),
remainingDays: Mod(weekDaysToAddAbs, 5),
daysToWeekend:
If(weekDaysToAdd<0,Weekday(startDate, StartOfWeek.Monday)
,5- Weekday(startDate, StartOfWeek.Monday))
},
With(
{ daysToAdd: fullWeeks * 7 + remainingDays + If(remainingDays > daysToWeekend, 2, 0) },
DateAdd(startDate, If(weekDaysToAdd<0,-1,1)*daysToAdd )))
) )
)

View solution in original post

10 REPLIES 10
Ramole
Super User
Super User

Hi @EdouardVH 

Do you want to exclude weekend ?
have look this post more https://powerusers.microsoft.com/t5/Building-Power-Apps/Exclude-the-weekends/m-p/901790 

Thank you
If this post helps, then Click on the Thumbs Up below . and Accept it as the solution . to help others find helpful.

Hi , @Ramole 

yes I would like to exclude the weekends and the days present in my sharepoint list.

The topics I find explain how to exclude weekends and days between two dates.

except that in my case I have only one departure date to which I add a number of days.

WarrenBelz
Most Valuable Professional
Most Valuable Professional

hi @WarrenBelz ,

 


Thank you for your help, !!

 

 

Yes I have read and tested, but it does not work.

Take the example if I select November 30, 2021 and I want to put -18 days I fall on the weekend. November 6, 2021

 

toto.png

Hi @EdouardVH ,

I don't think it was meant to have negative values.

Thanks @WarrenBelz ,

 

I would have liked to find a solution, it would have been my Christmas present 😂

Hi @EdouardVH ,

I will tag the author @timl here, but he will probably be offline due to his timezone.

timl
Super User
Super User

Hi @WarrenBelz - Thanks for tagging me and for linking my post. You're correct - most of these solutions are not designed to work with negative values.

The general technique relies on us calculating the number of working days based on full weeks, and to make an adjustment based on the number of partial days. The places where we 'hardcode' these additions would need to be subtractions in the case of where we want to subtract working days. Where we calculate the partial days, rather than calculate the number of days to the weekend, we need to calculate the number of days from the weekend since we're now counting backwards.

 

@EdouardVH - To cope with negative values, my initial thought is to base the calculation on the absolute positive value, and to introduce if statements to account for the negative variations. The code would look like this:

 

With({weekDaysToAdd: -18},
With(
    { weekDaysToAddAbs: Abs(weekDaysToAdd),
      startDate:Date(2021,11,30) },
    With(
        {
            fullWeeks: RoundDown(weekDaysToAddAbs / 5, 0),
            remainingDays: Mod(weekDaysToAddAbs, 5),
            daysToWeekend: 
            If(weekDaysToAdd<0,Weekday(startDate, StartOfWeek.Monday)
            ,5- Weekday(startDate, StartOfWeek.Monday))            
        },
        With(
            { daysToAdd: fullWeeks * 7 + remainingDays + If(remainingDays > daysToWeekend, 2, 0) },
            DateAdd(startDate, If(weekDaysToAdd<0,-1,1)*daysToAdd )))
   )
)

 

This produces the following result:

timl_0-1640347102591.png

This verifies the same formula against your original question of +45 days.

timl_1-1640347189184.png

 

Because @CarlosFigueira 's formula was neater, it was easier to add these variations to his formula so credit goes to Carlos.

To make the adjustment for vacation days, you can count the number of days and add that as a positive value to weekDaysToAddAbs.

 

Hi @WarrenBelz  ,  @timl , 

 

Sorry for the delay, Thank you very much for your help with my project.

 

@timl  can you confirm to me that adding the number of days to weekDaysToAdAbs is correct? 

 

Spoiler
With({weekDaysToAdd: -18},
With(
{ weekDaysToAddAbs: Abs(weekDaysToAdd),
startDate:Date(2021,11,30) },
With(
{
fullWeeks: RoundDown(weekDaysToAddAbs / 5, 0),
remainingDays: Mod(weekDaysToAddAbs, 5),
daysToWeekend:
If(weekDaysToAdd<0,Weekday(startDate, StartOfWeek.Monday)
,5- Weekday(startDate, StartOfWeek.Monday))
},
With(
{ daysToAdd: fullWeeks * 7 + remainingDays + If(remainingDays > daysToWeekend, 2, 0) },
DateAdd(startDate, If(weekDaysToAdd<0,-1,1)*daysToAdd )))
) + CountIf(Holiday;HolidayDate>=startDate;HolidayDate<=startDate) )
)

thank you very much 

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!   This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions in the Forums to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber of SolutionsSuper UsersNumber of Solutions @anandm08  23 @WarrenBelz  31 @DBO_DV  10 @Amik  19 AmínAA 6 @mmbr1606  12 @rzuber  4 @happyume  7 @Giraldoj  3@ANB 6 (tie)   @SpongYe  6 (tie)     Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersSolutionsSuper UsersSolutions @anandm08  10@WarrenBelz 25 @DBO_DV  6@mmbr1606 14 @AmínAA 4 @Amik  12 @royg  3 @ANB  10 @AllanDeCastro  2 @SunilPashikanti  5 @Michaelfp  2 @FLMike  5 @eduardo_izzo  2   Meekou 2   @rzuber  2   @Velegandla  2     @PowerPlatform-P  2   @Micaiah  2     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 3:Community MembersSolutionsSuper UsersSolutionsPower Apps anandm0861WarrenBelz86DBO_DV25Amik66Michaelfp13mmbr160647Giraldoj13FLMike31AmínAA13SpongYe27     Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 4:Community MembersSolutionsSuper UsersSolutionsPower Apps DBO-DV21WarranBelz26Giraldoj7mmbr160618Muzammmil_0695067Amik14samfawzi_acml6FLMike12tzuber6ANB8   SunilPashikanti8

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (1,268)