Unable to remove PowerBIIntegration

Hi,

 

I experimented with PowerBI integration within my app and am now having trouble removing this which is causing users to need a PowerBI license to use the app.

 

I've removed the data connector and do not have any PowerBI elements in the app, however there is a PowerBIIntegrator which I am unable to delete. Is there a fix for this or do I have to rebuild the app? or is there perhaps another way for users not to need a PowerBI license?

 

Thanks

Richard

1 ACCEPTED SOLUTION

Accepted Solutions
v-xida-msft
Community Support
Community Support

Hi @Anonymous ,

Do you embed a canvas app into your Power BI report?

Do you want to remove the ‘PowerBIIntegration’ option from your canvas app?

 

If you embed a canvas app into your Power BI report, and want to remove the ‘PowerBIIntegration’ option from your canvas app,  afraid that there is no way to achieve your needs in Power Apps currently.

 

The 'PowerBIIntegration' option represents the Integration between Power BI and Power App canvas app, means this canvas app is a Integration App, rather than a standard canvas app. Currently, there is no option to remove the 'PowerBIIntegration' option from the embedded canvas app. Also there is also no way to use the Power BI Integration Canvas app without Power BI license.

 

If you would like this feature to be added in Power Apps, please submit an idea to Power Apps Ideas Forum:

https://powerusers.microsoft.com/t5/Power-Apps-Ideas/idb-p/PowerAppsIdeas

 

As an fixed solution, you should re-create a new canvas app (standard canvas app) in your Power Apps Environment, then the 'PowerBIIntegration' option would not be shown up.

 

Regards,

Community Support Team _ Kris Dai
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

3 REPLIES 3
v-xida-msft
Community Support
Community Support

Hi @Anonymous ,

Do you embed a canvas app into your Power BI report?

Do you want to remove the ‘PowerBIIntegration’ option from your canvas app?

 

If you embed a canvas app into your Power BI report, and want to remove the ‘PowerBIIntegration’ option from your canvas app,  afraid that there is no way to achieve your needs in Power Apps currently.

 

The 'PowerBIIntegration' option represents the Integration between Power BI and Power App canvas app, means this canvas app is a Integration App, rather than a standard canvas app. Currently, there is no option to remove the 'PowerBIIntegration' option from the embedded canvas app. Also there is also no way to use the Power BI Integration Canvas app without Power BI license.

 

If you would like this feature to be added in Power Apps, please submit an idea to Power Apps Ideas Forum:

https://powerusers.microsoft.com/t5/Power-Apps-Ideas/idb-p/PowerAppsIdeas

 

As an fixed solution, you should re-create a new canvas app (standard canvas app) in your Power Apps Environment, then the 'PowerBIIntegration' option would not be shown up.

 

Regards,

Community Support Team _ Kris Dai
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Anonymous
Not applicable

Thank you for your reply on this. I don't have my app embedded on a power bi report. I only experimented with embedding a Power BI report into the app but have since removed this. From what you are saying Ill need to rebuild the app.

 

Richard

RusselThomas
Community Champion
Community Champion

This is such an old post but I noted this behaviour is still the case in today's platform.

 

For anyone else arriving here with the same question - please note - you can remove the PowerBIIntegration component by rolling back your app to a version before embedding it in Power BI. 

When you embed it the first time, Power BI asks you to open the app and save it - that action should create a new version, so if you roll back to the version just before this, it will remove the integration.

 

Obviously, if you created the app from within the BI visual then you won't have a version that isn't integrated, so this wouldn't work.  

 

Kind regards,

RT

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!   This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions in the Forums to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersNumber of SolutionsSuper UsersNumber of Solutions @anandm08  23 @WarrenBelz  31 @DBO_DV  10 @Amik  19 AmínAA 6 @mmbr1606  12 @rzuber  4 @happyume  7 @Giraldoj  3@ANB 6 (tie)   @SpongYe  6 (tie)     Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Community MembersSolutionsSuper UsersSolutions @anandm08  10@WarrenBelz 25 @DBO_DV  6@mmbr1606 14 @AmínAA 4 @Amik  12 @royg  3 @ANB  10 @AllanDeCastro  2 @SunilPashikanti  5 @Michaelfp  2 @FLMike  5 @eduardo_izzo  2   Meekou 2   @rzuber  2   @Velegandla  2     @PowerPlatform-P  2   @Micaiah  2     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 3:Community MembersSolutionsSuper UsersSolutionsPower Apps anandm0861WarrenBelz86DBO_DV25Amik66Michaelfp13mmbr160647Giraldoj13FLMike31AmínAA13SpongYe27     Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Week 4:Community MembersSolutionsSuper UsersSolutionsPower Apps DBO-DV21WarranBelz26Giraldoj7mmbr160618Muzammmil_0695067Amik14samfawzi_acml6FLMike12tzuber6ANB8   SunilPashikanti8

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (1,002)