Create a task when an Item is modified and update this item again when task is completed

Hi,

 

I'm trying to set a workflow but I'm having some troubles getting the task. 

I have an item in a list. If this item is modified (colum "Status" is modified to : "Get signatures"), then a task needs to be created. (This is working fine). But when THIS task is completed, I need to update my original item and modify the status from "Get signatures" to "Signed". 

I'm using the : update item, but not sure about how to get that task. 

 
 

flow item.png

8 REPLIES 8
chsanche
Community Support
Community Support

Hi @Eri_V 

 

There are triggers that fire the Flows when tasks are completed, there is one for Planner and one for Outlook, depending on where you are creating the task you could use one of these triggers to accomplish what you need.

Annotation 2020-04-22 141615.pngAnnotation 2020-04-22 141634.png

Best Regards,

--

If this reply has answered your question or solved your issue, please mark this question as answered. Answered questions help users in the future who may have the same issue or question quickly find a resolution via search. If you liked my response, please consider giving it a thumbs up. THANKS!

If this post helps you give a :thumbs_up: and if it solved your issue consider Accept it as the solution

Hi. Thanks for your answer. Yes, I know, I used that trigger but I don't know how to indicate the specific item that needs to be updated. 

Please take a look at my flow:

1- Once task is created, what should I do to indicate that if THAT task (specifically) is completed, then perform next action. I used the Get task, but not sure is the right way

2- Once task is completed, then, I run the : Update Item. I'm able to select the site, the list, but I don't know how to specify, that my first item (first trigger), needs to be updated. My flow is currently updating all items (which is not ok). 

  

v-alzhan-msft
Community Support
Community Support

Hi @Eri_V ,

 

One flow could only has one trigger, so you should create two flows. And you need to make sure the Title of task and item would be same and unique.

The first one when an item is modified in the list:

1.png

 

The second one when a tsk is completed.

2.png

 

Best regards,

Alice   

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

I'm getting the 400 error msg. Badrequest 

"status"400,
  "message""The expression \"ent 19\" is not valid.

 

ent 19 : name of my task and my item.  

 

My new 2nd flow: 

 

task 2.pngtask3.png

Hi @Eri_V ,

 

Please remove the Apply to each in your flow, just create the flow as my provided screenshot.

And provide the run history of the flow if the flow couldn't flow.

 

Best regards,

Alice   

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Thanks Alice, 

 

You were right. I modified the flow, but it's still showing up the same error msg. 

 

task9.png

 

errorerror

 

message""The expression \"ent 23\" is not valid. Creating query failed.\r\nclientRequestId: c8281df3-7348-441d-9666-d5f66792c30c\r\nserviceRequestId: c8281df3-7348-441d-9666-d5f66792c30c"
 
My first flow:  (two different flows as you've said)
 
task8.png
 
 

Hi @Eri_V ,

 

Your flow still wrong.

Why are you don't create the same as mine:

1.png2.png

 

Best regards,

Alice   

Community Support Team _ Alice Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi Alice,

You were right. I thought you were trying to highlight some info. such as the title. I should have ask. 

It's working. Thanks.

 

But now, I have an issue since I had to modify the task titles.

I'd need P.A to create at least 10 automatic tasks associated with each item depending on the performed actions. What I've done before your advice, is add some info. regarding the "task type" in the task title, i.e. Enterprise 1 - Get signatures. As you've suggested, I modified this approach and I set up the same Item title i.e: Enterprise 1

As you see, I'm no longer displaying: Get signatures. 

 

more details :  

Item: Enterprise 1 

Statuses: Submitted, Get signatures, Signed, Sent to committee, Approved by committee, Rejected by committee, Contract, Contract signed

 

With my new flow (thanks for that), an automatic task with the title: Enterprise 1 will be created. But this could confuse users and managers since they won't be able to understand at a glance if the task is associated with: get signatures or to do the Contract.

 

Any suggestions?   

 

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!    This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24  17 @Anil_g  7 @ManishSolanki  13 @eetuRobo  5 @David_MA  10 @VishnuReddy1997  5 @SpongYe  9JhonatanOB19932 (tie) @Nived_Nambiar  8 @maltie  2 (tie)   @PA-Noob  2 (tie)   @LukeMcG  2 (tie)   @tgut03  2 (tie)       Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate  @Deenuji  12@ManishSolanki 19 @Anil_g  10 @NathanAlvares24  17 @VishnuReddy1997  6 @Expiscornovus  10 @Tjan  5 @Nived_Nambiar  10 @eetuRobo  3 @SudeepGhatakNZ 8     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22   Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2   Anil_g2   SharonS2  

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages