cancel
Showing results for 
Search instead for 
Did you mean: 
Reply
mansi27
Frequent Visitor

Send email notification to user X days before a calculated date

Hi,

 

We have a sharepoint list with a calculated date column "Next Inspection Date". This column values are derived by adding 6 months to another column "Last Inspection Date" which is filled by the user. We are trying to automate and add an email notification that is sent 14 days before the calculated column date in "Next Inspection Date".

 

I am new to power automate and would love any help in terms of how to design the flow. I have tried using the inbuilt flow from sharepoint list but since the column I am trying to use is a calculated column it gives me an error.

 

Thanks for your help in advance 🙂

Mansi

1 REPLY 1

@mansi27 although you have a calculated column in your list this can't be used in the filter query so you need to do the calculation again in the flow.

 

So in this example there are 2 items where today (Sunday 2nd July) is 14 days before the next review date:

0-SP.png

 

Create a new instant cloud flow from blank and the trigger should be a recurrence schedule set to 1 day and select your timezone and the time you want the flow to run each day. Next add a compose action, click in the field and from the expression tab of the dynamic content box enter

formatDateTime(utcNow(),'yyyy-MM-dd')

- when doing date comparisons it is best to use the yyyy-MM-dd format. I've renamed the compose to Today.

1-Flow.png

 

Next. add a SharePoint get items action. I've entered LastReview ne null so it only brings back items where there is a date in the LastReview column (ne = not equal to).

 

2-Flow.png

 

Next add an apply to each and select value from the dynamic content box. All the following actions will be inside the apply to each.

 

3-Flow.png

 

Next, add 3 compose actions

 - For the first one select your last review column. I've renamed the Compose to LastReview.

 - For the second one enter the following expression which adds 180 days to the previous LastReview compose and formats it in the yyyy-MM-dd format. I've renamed the compose to Add180.
formatDateTime(addDays(outputs('LastReview'),180), 'yyyy-MM-dd')

 

- For the third one enter the following expression to take 14 days from the Add180 compose. I've renamed the compose to 14DaysAhead.
formatDateTime(addDays(outputs('Add180'),-14),'yyyy-MM-dd')

 

 

4-Flow.png

 

Next, add a condition.  For the left field select the outputs of 14DaysAhead and for the right field select the outputs of Today.

 

Leave the red if no channel empty. For the green if yes channel I've added another compose action to change the format of the date in the email and used the expression 

formatDateTime(outputs('Add180'),'dddd dd MMMM yyyy')

 

Finally add the send an email (v2) action.

5-Flow.png

 

Rename, save and test your flow. As you can see below the correct 2 emails were sent:

6-Email.png

 

Rob
Los Gallardos
If I've answered your question or solved your problem, please mark this question as answered. This helps others who have the same question find a solution quickly via the forum search. If you liked my response, please consider giving it a thumbs up. Thanks.

Helpful resources

Announcements

Community will be READ ONLY July 16th, 5p PDT -July 22nd

Dear Community Members,   We'd like to let you know of an upcoming change to the community platform: starting July 16th, the platform will transition to a READ ONLY mode until July 22nd.   During this period, members will not be able to Kudo, Comment, or Reply to any posts.   On July 22nd, please be on the lookout for a message sent to the email address registered on your community profile. This email is crucial as it will contain your unique code and link to register for the new platform encompassing all of the communities.   What to Expect in the New Community: A more unified experience where all products, including Power Apps, Power Automate, Copilot Studio, and Power Pages, will be accessible from one community.Community Blogs that you can syndicate and link to for automatic updates. We appreciate your understanding and cooperation during this transition. Stay tuned for the exciting new features and a seamless community experience ahead!

Summer of Solutions | Week 4 Results | Winners will be posted on July 24th

We are excited to announce the Summer of Solutions Challenge!    This challenge is kicking off on Monday, June 17th and will run for (4) weeks.  The challenge is open to all Power Platform (Power Apps, Power Automate, Copilot Studio & Power Pages) community members. We invite you to participate in a quest to provide solutions to as many questions as you can. Answers can be provided in all the communities.    Entry Period: This Challenge will consist of four weekly Entry Periods as follows (each an “Entry Period”)   - 12:00 a.m. PT on June 17, 2024 – 11:59 p.m. PT on June 23, 2024 - 12:00 a.m. PT on June 24, 2024 – 11:59 p.m. PT on June 30, 2024 - 12:00 a.m. PT on July 1, 2024 – 11:59 p.m. PT on July 7, 2024 - 12:00 a.m. PT on July 8, 2024 – 11:59 p.m. PT on July 14, 2024   Entries will be eligible for the Entry Period in which they are received and will not carryover to subsequent weekly entry periods.  You must enter into each weekly Entry Period separately.   How to Enter: We invite you to participate in a quest to provide "Accepted Solutions" to as many questions as you can. Answers can be provided in all the communities. Users must provide a solution which can be an “Accepted Solution” in the Forums in all of the communities and there are no limits to the number of “Accepted Solutions” that a member can provide for entries in this challenge, but each entry must be substantially unique and different.    Winner Selection and Prizes: At the end of each week, we will list the top ten (10) Community users which will consist of: 5 Community Members & 5 Super Users and they will advance to the final drawing. We will post each week in the News & Announcements the top 10 Solution providers.  At the end of the challenge, we will add all of the top 10 weekly names and enter them into a random drawing.  Then we will randomly select ten (10) winners (5 Community Members & 5 Super Users) from among all eligible entrants received across all weekly Entry Periods to receive the prize listed below. If a winner declines, we will draw again at random for the next winner.  A user will only be able to win once overall. If they are drawn multiple times, another user will be drawn at random.  Individuals will be contacted before the announcement with the opportunity to claim or deny the prize.  Once all of the winners have been notified, we will post in the News & Announcements of each community with the list of winners.   Each winner will receive one (1) Pass to the Power Platform Conference in Las Vegas, Sep. 18-20, 2024 ($1800 value). NOTE: Prize is for conference attendance only and any other costs such as airfare, lodging, transportation, and food are the sole responsibility of the winner. Tickets are not transferable to any other party or to next year’s event.   ** PLEASE SEE THE ATTACHED RULES for this CHALLENGE**   Week 1 Results: Congratulations to the Week 1 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge.   Community MembersNumber SolutionsSuper UsersNumber Solutions Deenuji 9 @NathanAlvares24  17 @Anil_g  7 @ManishSolanki  13 @eetuRobo  5 @David_MA  10 @VishnuReddy1997  5 @SpongYe  9JhonatanOB19932 (tie) @Nived_Nambiar  8 @maltie  2 (tie)   @PA-Noob  2 (tie)   @LukeMcG  2 (tie)   @tgut03  2 (tie)       Week 2 Results: Congratulations to the Week 2 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 2: Community MembersSolutionsSuper UsersSolutionsPower Automate  @Deenuji  12@ManishSolanki 19 @Anil_g  10 @NathanAlvares24  17 @VishnuReddy1997  6 @Expiscornovus  10 @Tjan  5 @Nived_Nambiar  10 @eetuRobo  3 @SudeepGhatakNZ 8     Week 3 Results: Congratulations to the Week 3 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 3:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji32ManishSolanki55VishnuReddy199724NathanAlvares2444Anil_g22SudeepGhatakNZ40eetuRobo18Nived_Nambiar28Tjan8David_MA22   Week 4 Results: Congratulations to the Week 4 qualifiers, you are being entered in the random drawing that will take place at the end of the challenge. Week 4:Community MembersSolutionsSuper UsersSolutionsPower Automate Deenuji11FLMike31Sayan11ManishSolanki16VishnuReddy199710creativeopinion14Akshansh-Sharma3SudeepGhatakNZ7claudiovc2CFernandes5 misc2Nived_Nambiar5 Usernametwice232rzaneti5 eetuRobo2   Anil_g2   SharonS2  

Check Out | 2024 Release Wave 2 Plans for Microsoft Dynamics 365 and Microsoft Power Platform

On July 16, 2024, we published the 2024 release wave 2 plans for Microsoft Dynamics 365 and Microsoft Power Platform. These plans are a compilation of the new capabilities planned to be released between October 2024 to March 2025. This release introduces a wealth of new features designed to enhance customer understanding and improve overall user experience, showcasing our dedication to driving digital transformation for our customers and partners.    The upcoming wave is centered around utilizing advanced AI and Microsoft Copilot technologies to enhance user productivity and streamline operations across diverse business applications. These enhancements include intelligent automation, AI-powered insights, and immersive user experiences that are designed to break down barriers between data, insights, and individuals. Watch a summary of the release highlights.    Discover the latest features that empower organizations to operate more efficiently and adaptively. From AI-driven sales insights and customer service enhancements to predictive analytics in supply chain management and autonomous financial processes, the new capabilities enable businesses to proactively address challenges and capitalize on opportunities.    

Updates to Transitions in the Power Platform Communities

We're embarking on a journey to enhance your experience by transitioning to a new community platform. Our team has been diligently working to create a fresh community site, leveraging the very Dynamics 365 and Power Platform tools our community advocates for.  We started this journey with transitioning Copilot Studio forums and blogs in June. The move marks the beginning of a new chapter, and we're eager for you to be a part of it. The rest of the Power Platform product sites will be moving over this summer.   Stay tuned for more updates as we get closer to the launch. We can't wait to welcome you to our new community space, designed with you in mind. Let's connect, learn, and grow together.   Here's to new beginnings and endless possibilities!   If you have any questions, observations or concerns throughout this process please go to https://aka.ms/PPCommSupport.   To stay up to date on the latest details of this migration and other important Community updates subscribe to our News and Announcements forums: Copilot Studio, Power Apps, Power Automate, Power Pages

Users online (817)